Majuba Silo recovery project

Client Majuba Power Station
Location South Africa
Scope Of Work Concrete sliding of silos, lift shaft and columns
Schedule 6 Months
Contractors Stefanutti Stocks

Project Detail

The project called for the sliding of a concrete silo and a lift shaft. Two more silos had skins slid to them as a recovery project. Two concrete columns were constructed using a climbing shutter system. This was a fast tract project which was completed in six months on time and within budget.

Be the first to track the progress on your project from anywhere around the world with our online login facility.
With our online monitoring system “Date and time Stamped” images can be viewed and downloaded remotely to a cellphone or PC. This data is sent directly to our server when the camera has taken a picture. A time lapse video of each day is produced for quick viewing and download of the days activities. This facility has proven to be of immense value for projects located in remote areas around the world. Individuals logging into the same image can now discuss issues on site when situated in different locations around the world.